TECHNOLOGY
Applying the vibro floor results in a rapid pace of work (up to 300-400 m2 per day finished flooring). A uniform surface with high solidity is obtained (1 MPA adhesion strength). It is widely used in large warehouses, factories, supermarkets, showrooms, automotive repair shops, etc.



STAGE 1
Laying and machine download of cement mortar
Laying and machine download of cement mortar
STAGE 2
Applying adhesive layer bonding cement mortar and tiles
Applying adhesive layer bonding cement mortar and tiles
- Dry method - contact layer of dry cement
- Wet method - contact adhesive cement layer type C1










STAGE 3
Tiling
- Granitogres tiles
- Clinker tiles and others
STAGE 4
Vibrating the already properly arranged tiles
Through high-frequency vibration, complete tile sealing is achieved.









STAGE 5
Machine grouting and cleaning the finished flooring
The finished floor is mechanically bonded using cement, epoxy resins depending on the environment.